Prototype Build Day 1: Structure and Mechanism

Focus question: How do engineers build the structure and core mechanism of a prototype?

Mission Briefing

Today’s Plan

Use this page with the lesson presentation, your engineering notebook, and the tools or evidence assigned for Build the Structure and Core Mechanism.

Learning Targets

  • Construct the main structure using the approved plan and materials.
  • Align the mechanism so it can move or transfer force as intended.
  • Document build changes, problems, and solutions.

Success Looks Like

You can build the prototype structure and mechanism while documenting construction evidence.

LaunchLearnApplyCheckSubmit
Opening Prompt

How do engineers build the structure and core mechanism of a prototype?

Connect your response to the decision, evidence, or quality standard required for Build the Structure and Core Mechanism.

Reveal: useful engineering move

This lesson is ready to move forward when the evidence meets this standard: The structure is stable and the mechanism can move through its intended basic range without the electrical subsystem.

Core Skill

What We Are Practicing

Key Idea 1

Build the functional structure before adding details.

Key Idea 2

Mechanism alignment affects reliability and motion quality.

Key Idea 3

Build notes should capture changes while they happen, not after they are forgotten.

Your Task

Build the Structure and Core Mechanism

Construct the prototype frame and main mechanical relationship while documenting deviations from the approved plan.

  1. Verify materials, tools, and dimensions before cutting or assembly.
  2. Build the structural base or frame.
  3. Install the primary mechanism and check free movement.
  4. Record one build change, issue, or confirmed dimension.

Quality check: The structure is stable and the mechanism can move through its intended basic range without the electrical subsystem.

Lesson Interactive

Sequence the Structural Prototype Build

Arrange the build steps to reduce damage, rework, and hidden fit problems.

Reorder the steps

  1. Install the moving mechanism
  2. Inspect fabricated parts
  3. Verify free movement
  4. Assemble the structural frame
  5. Dry-fit all interfaces

Move items with the arrow buttons. Permanent assembly should not happen before inspection and dry fitting.

Begin with part quality and fit. Build the structure before installing and checking the mechanism.
What You Will Submit

Mechanical Build Progress

  • One progress photo showing the structure and core mechanism.
  • A brief build note identifying a change or issue.

Submission standard: The structure is stable and the mechanism can move through its intended basic range without the electrical subsystem.

Resources

Lesson Resources

Presentation

Lesson 4.15 PowerPoint

Use the lesson slides for guided practice, interactive checks, and the exit ticket.

Course Hub

Introduction to Engineering Design

Return to the IED course hub for units, resources, certifications, and current course information.